TANZANIA ELECTRIC TRAIN LAUNCH DELAYED OVER POWER DAM

TANZANIA ELECTRIC TRAIN LAUNCH DELAYED OVER POWER DAM
Spread the love

Faith Nyasuguta 

Tanzanians will have to wait longer to use electric trains, thanks to delays in the completion of Julius Nyerere Dam set to produce electricity to power locomotive engines on the standard gauge railway (SGR).

Officials indicate that the construction schedule of the dam was re-done and the completion date postponed to 2024.

Instead of the service testing on the 300-kilometre Dar es salaam-Morogoro stretch of railroad set to be done this week, it will be done from August.

At the moment, engineers are examining the systems set to supply power to the locomotive engines on the line launched on Saturday. The examination is expected to be completed within three months.

This will be followed by the official launch of a passenger train, according to the Tanzania Railways Corporation (TRC). Two electric locomotive engines had been purchased by Turkish Construction Company Yapı Merkezi for use in testing on the line.

According to TRC head of public relations Jamila Mbarouk, people have been called upon to steer clear of the railway line during the testing period.

Tanzania’s Standard Gauge Railway was launched in 2018 /The East African/

It was revealed that the Rufiji River power project, which was scheduled to start operating in June and supply 2,115 megawatts of power, will be completed in 2024. 

Tanzania Electricity Corporation (Tanesco) Director-General Maharage Chande says that various challenges meant the $2.9 billion project’s timeline would need to be stretched to “sometime in 2024 at the earliest.”

A new deadline date for the dam’s launch will be determined after a joint project appraisal with the Egyptian contractors is completed, Mr Chande said.

The Director General noted that the postponement was not linked to project financing issues “but other factors.”

The dam located in the Stiegler’s Gorge on Tanzania’s Rufiji River is being built through a joint venture of two Egyptian companies, Arab Contractors and Elsewedy Electric.

Construction kicked off in December 2018 with an initial completion timeline of 42 months. Mr Chande’s announcement came against the backdrop of recent revelations in a government audit report that the power utility is facing compensation claims from the contractors over breach of contract. 

Controller and Auditor General (CAG) Charles Kichere’s findings show that frequent power cuts at the project site had caused work stoppages that resulted in the contractors lodging a $8.53 million claim with Tanesco.

According to CAG, the project was only 48.02 percent complete instead of the envisaged 94.47 percent by October 2021. Among reasons for the delay are Covid-19 pandemic, design and flooding of the Rufiji River.

Mr Chande said the project was 58.8 percent complete by March.

“The initial plan was to complete it by June but it has become obvious that is no longer possible. We are currently conducting an evaluation with the contractors to know when the dam can start generating electricity but all indications show it won’t be before 2024,” he said.

The Julius Nyerere hydropower station /CR/

Ahmed El-Assar, senior vice chairman of the Arab Contractors company, told an Egyptian government delegation visiting the project site in December last year that other challenges have included the location in a dense forest and difficulties in selecting the right manufacturer and exporter for the dam turbines.

At one point, heavy flooding on the Rufiji River also sunk some work equipment during construction of the project’s river diversion tunnel, Mr Assar told the delegation led by Egypt’s Housing Minister Assem El-Gazzar.

In August last year, the first of the nine turbines of 235MW capacity each was installed. Tanesco officials said in July last year that construction of a 400-kilovolt transmission line to a cooling substation in Chalinze, Coast region had already started to allow for immediate integration of electricity into the national grid once the dam starts operating.

The 160-kilometre transmission line was being built by an Indian firm, Larsen & Toubro Construction Company, the power company said. 

However, Energy Ministry sources confirmed that work on both the transmission line and cooling facility is also still far behind.